Wednesday, December 22, 2010

Sheetrock and Basement

The sheetrock crew completed their portion of the job today. Your blogger was finally able to enter the home. The home feels warm, tight and quite. It was cozy inside. I had to take a peek in the new basement area. It was warm and BIG. The ceilings are tall so you don't feel like you're in a cave. There's lots of storage tucked under the stairs.
Here are photos of the dining room,
upstairs landing, view from the dining room to the kitchen and the new upstairs bedroom. The sheetrock actually makes the rooms feel bigger.
















Tuesday, December 7, 2010

The Drywall is Hung

The drywallers worked all weekend and completed hanging all of the drywall. Today is a day of clean up in preparation for the tape and mud. We expect that process to take two weeks.








Friday, December 3, 2010

Drywall Load Day

It took a specialized boom truck to get the drywall up and near the second story window.









Four sheets of drywall just fit inside the window opening. The window was permantly installed today. The drywall crew didn't want to wait until Monday so they will be hanging the drywall over the weekend.




Thursday, December 2, 2010

Inside the Walls

This is the master bathroom water closet. As you can see, the framing dictated the placement of the light and fan.
The new vaccumm system is installed. Here's the upstairs hallway outlet.

The homeowners had a sink that backed up in the upstairs hall bathroom. The drain has been repaired. This is the laundry room side of the wall. You can also see a good view of a pocket door frame.


Main Floor Progress

The new entry hall closet goes straight back and takes a turn under the stairs. Its a great hiding place.
Here are the stairs to the basement. Note the sheer walls have been installed.

Our lead is bundled up today. He's pointing to the mud room pocket door hardware. The pantry entry is at the top of the stairs. Its going to be a good size for a pantry.


Bathroom Progress

We took the grand tour today. The house is much warmer with insulation. The site is cleaned up and ready for drywall. This is the master shower.
In the main floor bathroom we were able to remove the false ceiling and raise the ceiling. The bathroom has a whole new feel to it.




Wednesday, December 1, 2010

Insulation

The insulation has been installed. The inspection is set for tomorrow. Things will begin to happen fast now. Drywall will be "loaded" on Friday while the HVAC contractor turns on the heat. Look for new photos on Monday of the drywall being installed. Upstairs Hallway

Living Room
Kitchen Wall (they weren't quite done when this photo was taken)